Our Dream Park Timeline
I. Schematic Design Phase
a. Project Kickoff Dec. 20, 2022
b. Buildings Meeting Jan. 11, 2023
c. Splashpad Proposal Review Feb. 14, 2023
d. Progress Review Set March 14, 2023
e. 100% SD Set (TBD)
f. Project Review (City, P&R, Donors) June 1, 2023
II. Design Development Phase
a. Project Kickoff April 2023
b. 100% DD Set June 2023
III. Construction Document Phase
a. 60% Internal Set July 2023 (TBD)
b. Project Update to Parks Committee (TBD)
c. 80% Drawings Aug. 2023 (TBD)
d. 80% Project Review with City (TBD)
e. Final Plan Approval with City (If required)
f. Final Bid Documents Compiled Early Sept. 2023
g. Project Permitting/Submittals Aug.-Sept. 2023
IV. Bidding Phase
a. Ads for Bid Sept. 2023 (TBD)
b. Release Sept. 2023 (TBD)
c. Bid Opening Sept. 2023 (TBD)
d. City Council Awards Project Oct. 2023 (TBD)
e. Notice to Proceed Oct. 2023 (TBD)
V, Construction Phase
a. Mobilization/Start Mid/Late Oct. 2023
b. Substantial Completion July/Aug. 2024
c. A/E and Owner Project Review July/Aug. 2024
d. Final Completion Aug./Sept. 2024
VI. Open Park
a. Ribbon Cutting July 2024